Wales & West Utilities is starting work to upgrade gas pipes in the Plymstock Road area of Plymouth later this month.
The £750,000 work will start on April 19 and is essential to keep the gas flowing safely to heat and power local homes and businesses. Barring any engineering difficulties, it is due to finish in November.
Wales & West Utilities has liaised with Plymouth City Council to plan the work and, to minimise disruption, it has been agreed to complete the work in phases:
• Between April 19 and May 23 temporary four-way traffic lights will be in place on Dean Cross Road, Church Road, Horncross Road and Pomphett Road
• Between May 3 and June 28 temporary four-way traffic lights will be in place on Dean Cross Road, Dean Hill, Radford Park Road and Plymstock Road.
During this time a one-way system will also be in place between numbers 1-35 Randwick Park Road. Traffic will be able to enter from Plymstock Road only. Motorists are advised to allow extra time for travel.
Additional traffic management will be in place between July and November 2022 and the company will keep the local community updated as the work progresses.
Wales & West Utilities Fran Kirk is managing this gas pipe upgrade work. He said:
“We know that working in areas like this is not ideal, but it really is essential to make sure we keep the gas flowing to homes and businesses in the area, and to make sure the gas network is fit for the future.
“We’ll have a team of gas engineers on site throughout the project to make sure our work is completed as safely and as quickly as possible while keeping disruption to a minimum.
“While most of the gas network is underground and out of sight, it plays a central role in the daily lives of people across the Plymouth area. Whether it’s heating your home, making the family dinner or having a hot bath, we understand how important it is for your gas supply to be safe and reliable and there when you need it.
“This work is essential to keep the gas flowing to local homes and businesses today, and to make sure the gas network is ready to transport hydrogen and biomethane, so we can all play our part in a green future.”
Wales & West customer service team will take calls if residents have any questions about the work. You can contact them on freephone 0800 912 2999.